Frigate 126 on course
The construction of the future German frigate class is making good progress. The client and shipyard are cooperating at a high level. The F 126 project - formerly MKS 180 - reached the most important milestone in its realisation to date on 19 June 2020 after a multi-year award procedure in the European competition: the conclusion of the construction contract with the Damen Schelde Naval Shipbuilding shipyard. The project is currently focussing on the ongoing construction work. These are expected to progress to such an extent that production can begin at the end of 2023 and the keel can be laid for the first ship at the beginning of 2024. The construction contract provides for the procurement of four units as well as an option for two additional units for...